Hi marcosasilva@live.com,
Sorry, such an option is not possible at this moment; however, thank you for the suggestion. We will consider implementing it in the next ATENA versions.
Best regards.
You are not logged in. Please login or register.
Cervenka Consulting Forums → ATENA → Remote stopping the analysis → Post new reply
All fields with bold label must be completed before the form is submitted.
Hi marcosasilva@live.com,
Sorry, such an option is not possible at this moment; however, thank you for the suggestion. We will consider implementing it in the next ATENA versions.
Best regards.
Hi,
I'm running ATENA in batch mode and I've set load and displacement monitors. I'd like to know if it is possible to stop processing when the load between two consecutive steps falls by a certain amount (i.e. 50kN).
I know there are conditional break criteria, but they refer to convergence. What I'm trying to do is stop processing remotely when the load monitor shows a 10% fall. This would save me some time and memory.
thanks in advance